Project Schedule
|
| Date |
Activity |
| March 29, 2006 |
Environmental process begins - Notice of Intent (NOI) published in Federal Register |
| March 29-May 29, 2006 |
Public scoping period and comment period |
| May 9, 2006 |
Scoping meeting |
| August 2007 |
Alternatives Analysis |
|
November 2008 (see note 1) |
Draft EIS released for public comment |
| November 2008 (see note 1) |
Public Meeting |
| May 2009 (see note 1) |
Final EIS Publication |
| July 2009 (see note 1) |
Record of Decision |
| |
Note 1 — Schedule contingent upon release of anticipated grant funding in February 2008. |
|
|
|